A floating silt curtain is being added at the Black Rocks Harbor construction site on Saba to stop fine sediment from spreading into surrounding waters as work on the new harbour continues.
According to project manager Peter Bieremond of Public Entity Saba, the project’s environmental impact was studied before construction began, and various measures have been implemented to limit and compensate for that impact. Turbidity caused by excavation and breakwater construction is being followed closely and has mainly been contained within the project area, he said.

Supervising engineer Luc Jordens of Dutch engineering company Witteveen +Bos said siltation — fine soil particles — has been observed flowing out of the project area. “Though visible, the levels are low and kept within permissible limits,” he said.
Turbidity is being kept to a minimum through adjusted work methods and the construction of temporary bunds. It is monitored daily by a fixed monitoring buoy, as well as by manual measurements taken twice a day at three different locations. If permitted levels are exceeded, work is suspended.
Further restrictions apply during coral spawning season, including suspension of works, lower allowable turbidity levels and more frequent measurements.
As part of the project’s environmental measures, approximately 1,400 corals were relocated from the project area to an area near Hole in the Corner. The corals are being monitored regularly, and their survival rate has so far been very high. Other compensation measures include the addition of three marine protected areas to the Saba National Marine Park. Public Entity Saba has also allocated funds to Saba Conservation Foundation (SCF) and Saba Research Center to further protect marine life.
With work continuing and landside excavations scheduled for the coming months, Bieremond said higher levels of turbidity may be expected. The silt curtain is being installed as an additional measure to further reduce the amount of fine material flowing into the surrounding waters.
The yellow curtain will form a floating barrier around the work site. It is made of permeable fabric, measures 220 metres long and 10 metres high, and has been customised to the project’s specifications.
The buoys that will anchor the curtain have already been installed. The curtain has been prepared on land and will be towed into the water.
The Daily Herald.

Saba News News and Information from Saba Island, Dutch Caribbean